Single Span Bridge

Port Stephens Foreshore Drive bridge
13.7 x 9.6m SM1600 rated

  • 1.2m Abutments with 2.7m Wing walls 45 degrees
  • 1st InQuik bridge using stainless steel cladding 316 grade.
  • Budget $1.4 million – InQuik components $330K EXC GST

In March 2021 severe storms washed away the culvert along Foreshore Drive, Salamander Bay, forcing its closure. Construction of the InQuik bridge to reopen the road was completed 9 months later in time for the busy Christmas holiday season.

Project scope and guidelines

  • Replace collapsed culvert with a cost effective and suitable structure
  • The adjacent Mambo Wetlands is a treasured natural asset, so council needed to implement a construction methodology that was supportive of the environmentally sensitive conditions
    within a high profile public setting
  • Tight time constraint due to the collapsed culvert closing the road

The Mambo Wetlands Landcare and Conservation Group floated the idea of a Bailey Bridge, a type of portable, prefabricated, truss bridge, as a fix for the culvert in May.

Council reviewed this suggestion and other options due to the coastal location and sensitive environment. Port Stephens Council Group Manager Facilities & Services stated that the InQuik Bridge ticked all the boxes.

“We considered all options for the replacement of this culvert – an engineering project of this nature in an environmentally sensitive area is critical,” he said.

“It’s a prefabricated bridge, which expedites installation and minimises disruption to the environment. We’re not removing or disrupting parts of the estuary and the design doesn’t produce spoil or sulphate.

“The bridge creates a bigger channel for flood water to move through should we encounter a similar weather event in future. Better flow will also increase the water quality within the estuary.”

Project highlights

  •  Efficient installation and top down install in a sensitive environment
  • Stainless cladding to support the required design life in a coastal location
  • Enhance safety – separate 2.3m pedestrian shared path as this is a popular exercise and dog walking route.
  • InQuik components purchased via LGP 420 panel contract – with an experienced InQuik installer
Reids-Flat-Road-Timber-bridge
ULWilcox
Julong-Rd-Timber-Bridge

On the 13th August 2019 Upper Lachlan Shire Council in NSW advised that temporary load limits would come into effect for 12 timber bridges in the Shire. The temporary load limits had been based on advice from consulting firm Pitt & Sherry, which recently undertook an assessment of select bridges in the Shire to determine...

KBF1-1
IMG_0610-scaled
IMG_0606-scaled

Locally-made InQuik bridge improves access to Kingston Butter Factory arts precinct The InQuik system is fabricated locally in Brisbane, QLD and is a completely new way of building bridges. The solution provides an incredibly robust, long-lasting structure that requires minimal to no long-term maintenance. Click to download the Full Case Study. About The Kingston Butter Factory Precinct is...

Bourkes-Rd-Completion-Photo
IMG_0267
IMG_0262-scaled

Southern Downs regional bridge upgrades using InQuik to reduce project time, cost & complexity. The InQuik system is a completely new way of building bridges and provides an incredibly robust, long-lasting structure that requires minimal to no long-term maintenance. Southern Downs Regional Council identified the requirement to undertake the replacement of an existing single-lane timber...

SCC-Bridge-Rd-22
IMG_1675_1-rotated
file-upload-1594027198931

Shoalhaven City Council – NSW Bushfire Recovery: Rebuilding two destroyed bridges for Shoalhaven Council, using local contractors ‘InQuik’ time During the recent NSW bushfires some 60 Council-owned bridges were burnt or damaged, with the Currowan fire destroying four bridges on Shoalhaven Council’s road network. Two of the major bridges were School Creek – a 16m,...

IMG_2658
11
10

InQuik’s first bridge delivered in Victoria – Pyrenees Shire Council Bridge 59 Increasing load carrying capacity on key link roads is a high priority for Pyrenees Shire Council. The important part of achieving this goal is updating bridge infrastructure to cope with modern vehicles and increased tonnage. The latest route to have undergone an upgrade...