University of Wollongong, NSW (13.7×8.42m)

IMG_2272-scaled
UOW-5.10-54-scaled
UoW-Wgong
UOW-Complete-2-scaled
UOW-Complete-4-scaled
UOW-Complete-1-scaled
IMG_2266-scaled

Contractor: JBG Contractors

Abutments are 1.8m high (to the underside of the deck) with a 700mm stepped backwall that has an open front face for integration with the deck panels. Each abutment is connected to 2 x Magnelis-clad wing walls that are 2.5m high (to the top of the deck) and 2.7m-long, angled at 45 degrees to the abutments.

The bridge is a double-lane bridge with a pedestrian crossing.

Project Description: P5 car park extension 

The University released a tender for the construction of a bridge to improve access to a new car park within the technology campus. The InQuik product was chosen by JBG as it would enable them to meet the timeframe to delivery on the broader project as the bridge was a small but crucial part of the upgraded parking.

Key Project Points

  • Local suppliers and JBG delivered the project on time and within budget
  • The integral design minimises maintenance costs and was safer to install
  • The pre-engineered modular design allowed for 8.42m width and only lightweight cranes required for the “place and pour” install process.
Location:
University of Wollongong, NSW
Client:
University of Wollongong
Span and Width:
13.7m x 8.42m
Start Date:
End Date: